Freire Shopping Centre

Construction of the Freire shopping centre began on October 16, 2017.

The project entails the installation of 1,200 T of rebar and will take five months to complete. Our Torres Ocaranza AGF SpA division in Chile is in charge of this project. 

The shopping centre has an underground parking lot and two floors of stores. It is located in Curicó, a city in Chile’s VII region, home to 105,000 people.

For the installation of the A63-42H high-adhesion reinforcing rods, the division will hire 30 workers from Peru. Construction must comply with technical specifications specific to Chile, where seismic activity is common.

Here are some photos of the project under construction.

MALL CENTRO COMERCIAL FREIRE

El 16-10-2017 se da comienzo a la construcción del centro comercial Freire, obra en la cual se tienen que instalar 1200 Tn en un plazo de 5 meses.

Este Mall consta de un subterráneo destinado a aparcamiento y dos plantas destinadas a tiendas.

Se encuentra ubicado en Curicó ciudad perteneciente a la VII región – Chile, una ciudad que consta de 105.000 habitantes aprox.

Para la realización de la instalación de acero corrugado A63-42H en esta obra se considera una dotación de 30 trabajadores traídos desde Perú y se construye considerando las especificaciones técnicas de un País como Chile el cual tiene grandes movimientos sísmicos.