Categories Date

Immediate Takeoff

This autumn, AGF Steel was awarded a new contract as part of a major $2.5 billion expansion project at Montréal-Trudeau Airport.

The objective of this project is to more effectively manage the growing affluence of passengers, which rose to 18 million people in 2017.

The first phase of the project consists in revitalizing the parkade located in front of the terminal, with the addition of covered parking spaces.

To this end, AGF Steel will supply and install 5300 MT of reinforcing steel on a 12-week schedule.

The first reinforcing bars were delivered during the week of October 29, 2018.

We wish Magalie De Blois (Senior Detailer), Luc Voisard (Foreman), and the entire team involved in this project the best of success!

Despegue inmediato

Este año, Acier AGF obtuvo un nuevo contrato como parte de un proyecto de ampliación del Aeropuerto Montreal-Trudeau, cuyo presupuesto total se eleva a 2.5 mil millones de dólares.

Este programa tiene como objetivo administrar mejor la creciente afluencia de pasajeros, la cual se elevó a 18 millones de personas en el 2017.

La primera fase de los trabajos es sobre la revitalización del estacionamiento de varios niveles enfrente de la terminal, con la añadidura de espacios de estacionamiento cubiertos.

Para ello, Acier AGF proporcionará e instalará 5300 toneladas de acero de refuerzo en un plazo de doce semanas. Las primeras barras de refuerzo se entregaron durante la semana del 29 de octubre de 2018.

Mucho éxito para Magalie De Blois (Técnica, Encargada de Proyecto, Sénior), para Luc Voisard (Contramaestre) ¡y para todo el equipo implicado en este proyecto!