Structural work on the Curicó Provincial Hospital, a project by OHL Chile, began in February 2017. It is located in Curicó, a city in Chile’s VII region.

The hospital represents a huge step forward for Curicó and will be the most emblematic building in this city of 105,000 people. It covers more than 100,000 m2 and seven storeys (five above ground and two below) and has a budget of $204 million Chilean pesos.

  

The structural work must be completed in 18 months. It calls for 8,500 T of A63-42H reinforcing bars and will be erected on pillars and conventional slabs. This method of construction allows for pre-assembly of the pillars for the entire building. 

Construction company : OHL, Chile
Start : february 2017 - End : August 2018

HOSPITAL PROVINCIAL CURICO

En febrero se da comienzo a la obra gruesa del Hospital provincial de Curico para la empresa OHL sucursal Chile. Se encuentra ubicado en Curico , ciudad perteneciente a la VII region.

Este Hospital supone un gran avance pàra la ciudad y pasa a ser la construcción mas emblematica en esta ciudad la cual consta de 105.000 habitantes aprox.

Consta de mas de 100.000 metros cuadrado y 7 plantas , (dos subterráneos y cinco pisos ) y tiene .un presupuesto de 204 millones de pesos Chilenos.

La obra gruesa tiene un plazo de ejecución de 18 meses , la cantidad de acero corrugado A63-42H es de 8500 tn y se vasa en la realización de pilares piso a piso y losas tradicionales . Este sistema de construcción permite la realización del prearmado de los pilares de todo el edificio.

CONSTRUCTORA – OHL CHILE
COMIENZO: FEBRERO 2017 – FINALIZACION: AGOSTO 2018