Winning Contracts at the Champlain Bridge

AGF Du-For is proud to announce the winning of two major contracts at the Champlain bridge. The work involves the provision of several accesses for the workers assigned to the repair of concrete beams and decks. The work should take place over a period of two years, with most of it to be completed in 2014. The value of both contracts amounts to more than one million dollars.

Our team work has made a difference in obtaining and getting through that project: from the sales team to the yard where the material was prepared for shipping, and to the work team on site. As of September 30, the installation was 90% complete, and the dismantling should take place progressively before winter, depending on how the work progresses.